"Pressue VOC every Tank gradually adjust high, since the furnace insin VCM1, moved the plant VCM2 instead 07.00 am contact TPC. UT. To get pressure VOC increased.And the time 07.20 am pressure increase = 20-25 mm2HO time 07.45 am = 38 mm2HO every time Tank 07.55 am = 40-41 mm2HO contact. SUP. Water to rise again.Time 08.30 am pressure punch down, but the time 09.20-09.50 am pressure high every Tank has fitted to TPC again until the time of 10.11 am. Pressure VOC gradually reduced.As usual (time 10.00 am the TPC move to get pressure VOC from plant VCM2 are plant VCM1 instead).